WINONA ELEMENTARY General Contractor: Alliance Construction Solutions Project Manager: John Parks Superintendent: David Plumb This project was an administrative and classroom addition to the Winona Elementary School in Loveland. It involved importing and placing approximately 10,000 tons of stuctural fill for the new building pads. We also installed a new fire service, new fire hydrant, new sewer service, and an additional parking lot.
Site Demolition & Clearing
Excavation to Bottom of Footing & Structural Fill Import
Rough Grading for New Parking Lot
New Sewer Service
4" of Under Slab Gravel & Fine Grading
Water Main Tap for New 6" Fire Service
Asphalt Patching @ New Fire Service
Fine Grading for New Parking Lot |